STRUCTURES

On this page you will find all the stages of the setting up of the building’s structures.
A team of 7 to 12 permanent workers throughout the structural works phase.
28 oversized concrete pillars and 210 m of horizontal reinforced concrete beams form the structure of the ground floor and the 3 floors.
Each level consists of a concrete slab with a total surface area of 2,175 m² (2,270 m² – 90 m² stairs and skylights).

Ground floor

First floor

Second floor

Third floor